Maharashtra's Forest Department ordered work to stop at Adani Green Energy's 1,500 MW Tarali pumped-storage project in Satara on November 13, 2026, citing the absence of prior National Board for Wildlife approval. The decision followed an investigation by The Indian Express into a filing showing ₹56.75 crore against an earlier ₹5,675 crore project estimate, potentially reducing a wildlife conservation contribution from ₹227 crore to ₹2.27 crore. Adani maintains the smaller figure covers preliminary surveys rather than the full project. Forest Minister Ganesh Naik subsequently met company representatives, and officials began reviewing the explanation and possible withdrawal of the stop-work order.

Adani Tarali Project Halted in Satara: ₹227 Crore Wildlife Fund Dispute Raises Wider Environmental Concerns

The Maharashtra Forest Department’s stop-work order against Adani Green Energy has intensified scrutiny of wildlife clearances, project valuations and environmental disputes surrounding major power projects.

Maharashtra’s Forest Department has halted Adani Green Energy’s 1,500 MW Tarali pumped-storage project in Satara, citing construction activity without mandatory National Board for Wildlife approval.

The November 13 stop-work order followed revelations that the company sought to revise the declared project cost from ₹5,675 crore to ₹56.75 crore.

Documents examined by The Indian Express indicate that the revision would reduce the proposed Sahyadri Tiger Reserve conservation contribution from ₹227 crore to ₹2.27 crore.

The project lies within the deemed eco-sensitive zone associated with Koyna Wildlife Sanctuary, although Adani Green Energy disputes that its land requires additional wildlife-related restrictions.

Deputy Conservator of Forests Amol Satpute issued the stop-work notice, seeking an explanation within three days about construction allegedly undertaken without National Board for Wildlife clearance.

The developments have renewed questions about environmental safeguards, regulatory oversight and the relationship between large-scale electricity infrastructure and conservation responsibilities across ecologically sensitive Indian landscapes.

Tarali Project Cost Revision and Wildlife Clearance Dispute

The Union Environment Ministry recorded the Tarali project cost at ₹5,675 crore while recommending environmental clearance on February 11, 2025, according to official correspondence.

In March 2026, Maharashtra forest authorities sought a four-per cent conservation deposit, amounting to ₹227 crore, for protection measures connected with Sahyadri Tiger Reserve.

On September 8, 2026, the company submitted a notarised affidavit seeking recognition of ₹56.75 crore, prompting questions about the calculation of conservation contributions.

Satara honorary wildlife warden Rohan Bhate filed a complaint on October 30, challenging the revised figures; the Union Environment Ministry ordered a priority inquiry on November 6.

Adani Green Energy has rejected allegations of wrongdoing, maintaining that ₹56.75 crore represented preliminary site survey and investigation expenses rather than the overall capital expenditure.

The company cites a January 23, 2024, no-forest-land certificate, February 2025 environmental clearance and April 2025 consent to establish as evidence supporting its position.

It maintains the site occupies private, non-forest land approximately 3.2 kilometres from Koyna Wildlife Sanctuary, outside notified protected areas, buffer zones and eco-sensitive boundaries.

Adani acknowledges that its wildlife clearance proposal remains pending before the National Board for Wildlife, while disputing the allegation that construction violated applicable statutory requirements.

Also Read: Thousands Gather at Mumbai's Azad Maidan Seeking Medical Treatment and Release for Asaram Bapu

Environmental Disputes Extend From Maharashtra to Bihar and Assam

At Malshej Ghat, more than 500 villagers from Junnar reportedly demonstrated outside the Maharashtra Pollution Control Board office in Pune during August 2026.

The protesters opposed the proposed 1,500 MW Malshej Ghat Bhorande pumped-storage project, alleging inadequate Gram Sabha consultation; the scheduled public hearing was subsequently postponed.

In Bihar’s Pirpainti, Adani Power’s 2,400 MW thermal project faces disputed tree-loss estimates, including allegations raised before the National Green Tribunal by petitioner Sharvan Singh.

His petition estimates between five lakh and ten lakh affected trees, while a Forest Department communication cited by an NGT committee identifies 19,388 trees.

Congress has separately alleged that 1,050 acres were leased for 33 years at ₹1 annually, an accusation rejected by the Bihar government as politically motivated.

Authorities maintain that the bidding process was transparent, while the land-allocation allegations and differing environmental impact estimates remain matters requiring careful documentary scrutiny and verification.

In Assam’s Chapar, the Dhubri Forest Division issued an October 2026 tender concerning the felling of 407 trees for a proposed 3,200 MW project.

The tender reportedly estimated expenditure at approximately ₹8 lakh, adding to scrutiny of vegetation clearance associated with industrial development in the northeastern state.

Meanwhile, Maharashtra’s State Board for Wildlife recommended 136 hectares of tiger corridor land for the 400-kV Raipur–Tiroda transmission line, potentially affecting 5,152 trees.

That recommendation is not final wildlife clearance; approval from the National Board for Wildlife remains necessary before the project can proceed under applicable requirements.

The Tarali investigation and related proceedings will test how regulators reconcile electricity infrastructure development, transparent project accounting, community participation and legally mandated ecological protection.